Works May

In accordance with the fire prevention plan, this year we have had to carry out a maintenance cleaning to comply with the plan’s requirements for the summer season. To do so, our staff and equipment has been cleaning the green areas to fulfil the fire prevention plan. The green areas that have been done this year are:
Fiesta Día de Sitio de Calahonda
Summary of the informative meeting 6th of February.
Línea Verde ayuntamiento de Mijas
Gully refill in calle José de Orbaneja

Initially and due to the lack of pavements in our urbanisation, to finish off the road, a gullies were built to avoid the rain water running into dwellings and plots. This was also something specified on the bylaws and we were obliged to build them. At present, you will have noticed that there is no… [Read more]
Works in November

The works carried out in November have depended on the weather. Due to all the rain, our work has been delayed, while other jobs have been because of the rain. Due to the rain there has been a landslide in calle Andalucía that has been solved by our JCB. We have changed one of the… [Read more]
Works October 2018

In October we continue with the palm tree pruning. Last month our staff started pruning the smaller palm trees and now the taller ones are being done by a specialised company. We have also cut back some eucalyptus trees that had become dangerous. At present, we are carrying out the pine tree treatment as it… [Read more]
“Captain Day” golf tournament- Saturday 6 October
Works August 2018

As last month, in August we continue to focus our efforts on the cleaning of the urbanisation, streets, bins, etc. Also the green areas and we have basically completed our fire prevention plan which we are extending to other areas where we have found rubbish dumped by antisocial people. We have also cleared the paths… [Read more]